WSD Bond Update - August 22, 2018

In May 2015, the Woodburn community approved a $65 million bond. We continue to make progress on bond-funded projects to add space for students, make major repairs to maintain our schools, and improve security/technology systems. These proposed projects are scheduled along a 5-year timeline (2015-2020) for completion.

Summertime is a busy time for Woodburn School District and its contractors to complete new construction and major upgrades to schools while the students are at home. With the end of summer approaching it has been a mad dash to complete everything as planned, and managing our schedule even with construction booming across the state. We may need everyone to practice patience as final details of this summer's projects are completed, as well as with other school projects just getting under way. The good news is that we’re going to be ready for the start of the school year 2018-19!

Washington Elementary

Construction of a 2-story addition is nearly complete on the Washington Elementary site, which includes underground water lines for fire suppression system; Fire Department access roads; storm water management system; new covered play area; bus turn-around and staff parking; and a new gymnasium building. Bathrooms throughout the school have been upgraded to be accessible to all. At present the contractors are on site, working on the finishing touches and a final clean. And before they leave, they’ll test the new kitchen equipment that has been installed in the Cafeteria. Also, irrigation and landscaping is going in around the new buildings. We can’t wait to welcome staff and students back to this school next month!

[Photo: multipurpose room]

Concurrent with the interior work underway that was funded by the school bond, seismic upgrades are being made at Washington Elementary that were majorly financed by a grant received. In 2017, the Woodburn School District was awarded two grants totaling $3 million from the Infrastructure Finance Authority in 2017. The funds will be used for seismic upgrades to Washington and Lincoln Elementary Schools. The community’s approval of the bond in 2015 helped the school district leverage some of the funding from the Seismic Rehabilitation Grant Program.

We just posted photos today, and more will be coming soon to the dedicated album on Facebook. Please visit here!

If you’d like to check in on the progress, the school district has a web camera on the site so you can follow along day-to-day! To see what’s going on in real-time, please visit www.woodburnsd.org/bond-updates.

Success High School 

The new high school building for the Success High School is nearly complete! The new school was built adjacent to the Welcome Center/District Office on Meridian Drive. The solar array has been installed to provide green energy, as well as educational opportunities. The contractor has recently completed the parking lot asphalt and striping. Final installations will include kitchen equipment and carpet/flooring. The building is on track to be ready for the 2018-19 school year!

Please check out our new album for the most recent photos. We’ve dedicated an album on Facebook to all the construction photos at Success High School, please visit here!

If you’d like to see daily progress, you can follow along and watch online the new Success high School take form. Just visit the BOND UPDATES page on the website (www.woodburnsd.org/bond-updates) and check out what’s going on!

*If you are viewing the camera on an internal WoodburnSD.org server, please visit the page at: http://172.26.20.54/

Summer Projects 2018

Other upgrades and repairs that have been underway this summer include:

Nellie Muir Elementary 

• Replacement of HVAC (heating, ventilation, and air conditioning) system – The new rooftop mechanical units have been ordered and will be placed on the roof once delivery has been made in approximately 8-12 weeks

Lincoln Elementary

• Seismic upgrades

• Replacement of windows

French Prairie Middle School 

• Reconstruction of Library wall

• Installation of new windows/siding – so far 62 of 74 windows have been delivered and the installation will be completed this week. Next week the contractor will finish the interior trim of the windows and install exterior siding.

• Replacement of Cafeteria flooring – the existing flooring has been abated; the new flooring is on order and will be scheduled soon for installation.

Woodburn High School 

• Installation of final phase of fire sprinklers