WSD Bond Update - June 28, 2018

In May 2015, the Woodburn community approved a $65 million bond. We continue to make progress on bond-funded projects to add space for students, make major repairs to maintain our schools, and improve security/technology systems. These proposed projects are scheduled along a 5-year timeline (2015-2019) for completion.

Washington Elementary 

Construction of a 2-story addition is underway on the Washington Elementary site, which includes underground water lines for fire suppression system; Fire Department access roads; storm water management system; new covered play area; bus turn-around and staff parking; and a new gymnasium building.

In the classroom building, the Acoustic Treatment was recently installed, as well as the sprinkler system. In the multi-purpose room/kitchen, the plumping and electrical has been roughed in, as well as the wood framing completed. And, the kitchen equipment has been ordered. After the interior is finished, the equipment will be installed. On the exterior, the downspouts, canopies and exterior sidewalks have been underway. Next up is the completion of these features.

Over at the new gymnasium, interior lighting, exterior glazing, and the gym floor have progressed. This month the contractors are continuing work on the interior and installation of gym equipment.

With the release of staff and students the contractor has received approval to begin demolition of the remaining areas still needing to be completed. This work includes the demolition of the kitchen and cafeteria space for the transformation into a new school library. The contractor is also working to complete restroom upgrades as well as classroom upgrades within the existing building.

We just posted photos today, and more will be coming soon to the dedicated album on Facebook.  Please visit here! 

If you’d like to check in on the progress, the school district has a web camera on the site so you can follow along day-to-day! To see what’s going on in real-time, please visit  www.woodburnsd.org/bond-updates.

Success High School 

A new high school building for the Success High School is underway. It will have a community meeting space included in construction. The Groundbreaking ceremony was held on November 8, 2017. Completion is expected by September 2018 in time for the next school year.

On the campus, a solar array is being installed to provide green energy, as well as educational opportunities. Just recently the equipment pads were constructed to prepare for the installation of the racks that will hold the solar panels.

On the high school building, the exterior masonry wall has been constructed. Inside the building is where a lot of work is taking place now. Interior drywall has been hung, insulation and the fire sprinkler system has been installed. Contractors are working diligently in preparing to complete the interior phases of the project including electrical and mechanical finishes, painting and flooring installations.

Exterior finishes and site utilities are now in full swing as the contractors work to prepare and install hardscape and sidewalks, irrigation systems and place the landscaping around the new high school facility.

Please check out our new album for the most recent photos. We’ve dedicated an album on Facebook to all the construction photos at Success High School, please visit here!

If you’d like to see daily progress, you can follow along and watch online the new Success High School take form. Just visit the BOND UPDATES page on the website (www.woodburnsd.org/bond-updates) and check out what’s going on!

*If you are viewing the camera on an internal WoodburnSD.org server, please visit the page at: http://172.26.20.54/

Nellie Muir Elementary

Invitations to bid on the roofing project and HEATING, VENTILATION, AND AIR CONDITIONING SYSTEM upgrade have gone out. Once the bids are received, approved and a contract is in place, a timeline for completion will be established. BLRB Architect and project manager are continuing planning with staff at Nellie Muir to confirm that school-specific needs are considered.

BLRB Architects is working with District staff at Nellie Muir Elementary to develop the conceptual design documents for the capacity expansion project. With a concentrated effort being made to make sure the improvements will meet the school’s students’ and staff’s specific needs.

Heritage Elementary/Valor Middle School

At Valor, the Request for Proposals was issued in May. The architectural services contract will be awarded to OH Planning and Designs. Upon completion of the Contract Documents the project manager and Oh Design will the programming initiating the beginning of the Design phase of the project.

BLRB Architects is working with District staff at Heritage Elementary to develop the conceptual design documents for the capacity expansion project. With a concentrated effort being made to make sure the improvements will meet the school’s student s and staff’s -specific needs.

Lincoln Elementary/French Prairie Middle School

Seismic Upgrade Project: The District received grant funds to complete a seismic upgrade project at Lincoln Elementary. The work that currently is in progress includes installation of seismic connections and joints throughout the school building. There are several portions of this work that is being completed in association with the Bond projects. The work being completed in coordination with the seismic upgrade include asbestos abatement, window replacement and interior finish selections to match the District wide planning.

Planning is continuing with staff at Lincoln Elementary to make sure the annexation building design meets the needs of students and staff. For French Prairie Middle School, an invitation to bid was developed for the replacement of the cafeteria flooring and window upgrades. Planning is continuing with staff to make sure that upcoming projects address current and future needs at French Prairie.

Woodburn High School

This summer break will see the completion of the fire sprinkler installation in the high school building. We’ll share pictures of this project later this summer as it progresses.

Reminder: Photo Album on Facebook! 

Recent photos from construction projects are regularly added to the album on Facebook. To view, visit www.facebook.com/wsd103. (Updated: June 28, 2018)

---