WSD Bond Update - August 2017

In May 2015, the Woodburn community approved a $65 million bond. We continue to make progress on bond-funded projects to add space for students, make major repairs to maintain our schools, and improve security/technology systems. These proposed projects are scheduled along a 5­-year timeline (2015-2019) for completion.

Summer Construction Progress 

Superintendent Chuck Ransom recently sat down with the Woodburn Independent to discuss the construction projects that were underway this summer.  

"Woodburn students returning to school Sept. 5 may have spent their summers relaxing, but it's been a busy three months for construction crews working on projects funded by the $65 million school bond passed by voters in 2015.

John O. Henri, the project manager for the district's bond projects, outlined the progress at the Aug. 17 school board meeting and before the Aug. 23 Bond Advisory Accountability Committee. Although there are still things to finish up before class begins next week, it's looking like the school district will finish what it set out to accomplish during summer construction season." To read more, click here.

New pics in Photo Album! 

New photos from recent construction projects have been added to the album on Facebook. To view, visit www.facebook.com/wsd103.

---